Goldbach Development managed land acquisition, due diligence, and HCL PUZ approvals, along with obtaining construction and roundabout permits. The company also prepared the PTh for a large food retailer in collaboration with Goldbach Design & Build, supporting commercial growth and infrastructure development in the area.
Beneficiaries:
Large Food Retailer, Non-Food Gallery
Developed Land Area:
35,000 m²
Authorized Built Area:
5,500 m² + circulation areas and green spaces
Jobs Created:
80
Goldbach Development Activities:
Land identification and acquisition
Due diligence processes
Preparation and obtaining of Local Council Decision for Zonal Urban Plan approval
Obtaining construction permits, including the roundabout permit
Preparation of technical execution project for a large food retailer (in collaboration with GOLDBACH DESIGN & BUILD)
Project summary:
The Caracal project in Olt County was successfully completed, covering 35,000 m² of land with an authorized built area of 5,500 m² for a large food retailer and a non-food gallery, creating 80 jobs. Goldbach Development managed land acquisition, due diligence, and Local Council Decision for Zonal Urban Plan approvals, along with obtaining construction and roundabout permits. The company also prepared the technical execution project for the large food retailer in collaboration with Goldbach Design & Build, supporting commercial growth and infrastructure development in the area.
The Balș project in Olt County was successfully completed, covering 24,000 m² of land with an authorized built area of 5,500 m² for a large food retailer and a non-food gallery, creating 100 jobs. Goldbach Development handled land acquisition, due diligence, and permit approvals, including the demolition of 10,000 m² of existing buildings.
The Brașov project was successfully completed, covering 22,000 m² for a large food retailer and 14,500 m² for Brașov Retail Park, with an authorized built area of 6,250 m² for the large food retailer and 5,600 m² for the retail park, creating 110 jobs.
The Brăila project was successfully completed, covering 6,100 m² of land with an authorized built area of 1,500 m² for a large food retailer, creating 15 jobs. Goldbach Development managed the preparation and acquisition of building permits (AC), approvals for electric, water, and sewerage connections, and PTh preparation for the large food retailer.
Goldbach Development managed land acquisition, due diligence, and HCL PUZ approvals, along with obtaining construction and roundabout permits. The company also prepared the PTh for a large food retailer in collaboration with Goldbach Design & Build, supporting commercial growth and infrastructure development in the area.
The Constanța project was successfully completed, covering 18,000 m² of land with an authorized built area of 6,850 m², and a total developed area of 13,850 m², including circulation areas and green spaces for a large food retailer, creating 30 jobs. Goldbach Development managed the preparation and acquisition of building permits (AC), approvals for electric, water, and sewerage connections, and PTh preparation for the food retailer.
The Giurgiu project was successfully completed, covering 25,500 m² of land, with an authorized built area of 5,500 m² for a large food retailer and 6,000 m² for the commercial gallery, creating 60 jobs.
The Hațeg project was successfully completed, covering 29,000 m² of land with an authorized built area of 7,800 m², including circulation areas and green spaces for a large food retailer, creating 30 jobs. The project involved land identification, acquisition, and due diligence, securing HCL PUZ approvals, and obtaining permits for a 450-meter water pipeline diversion (€1.1 million cost) and a roundabout.
The Pitești project was successfully completed, covering 42,500 m² of land, with an authorized built area of 5,550 m² for a large food retailer, 6,650 m² for the commercial gallery, and 9,750 m² for a large non-food gallery, creating 110 jobs.
The Urziceni project in Ialomița County was successfully completed, covering 20,000 m² of land with an authorized built area of 5,460 m² for a large food retailer, creating 100 jobs. Goldbach Development managed land acquisition, due diligence, and HCL PUZ approvals, including the demolition of 3,000 m² of existing buildings.
The Turnu Măgurele project in Teleorman County was successfully completed, covering 43,000 m² of land with an authorized built area of 14,000 m² for two large food retailers and a non-food gallery, creating 140 jobs. Goldbach Development managed land acquisition, due diligence, PUZ approvals, and permits, including the demolition of 7,000 m² of existing buildings. The company also prepared the PTh for the food retailers in collaboration with Goldbach Design & Build, contributing to sustainable commercial expansion in the region.
The Târgoviște project in Dâmbovița County was successfully completed, covering 26,000 m² of land with an authorized built area of 5,500 m² for a large food retailer, creating 110 jobs. Goldbach Development handled land acquisition, due diligence, and HCL PUZ approvals, along with obtaining demolition and construction permits.